From Roadblock to Go-Live: Test Management for a Business-Critical Contact Centre Migration in the Insurance Industry

Written by Samuel Kraßnitzer | Jul 27, 2026 12:35:28 PM

If the contact centre goes down, customers cannot reach the insurer. With several thousand customer advisers operating nationwide around the clock, there is no margin for error.

 

Business-Critical Infrastructure with No Margin for Error

The Contact Centre Infrastructure division of one of Germany’s leading primary insurers is responsible for ensuring the high availability of its communication systems. The aim of the project was to replace the existing Skype-based telephony solution with Microsoft Teams.

What appeared to be a straightforward software migration proved significantly more complex in practice. Behind the scenes, numerous services had to be integrated, systems adapted and an Azure cloud integration implemented.

 

A Project That Failed to Gain Momentum

The deliverables provided by the external software developer failed to meet the requirements in terms of both quality and schedule. The project structure was unclear, responsibilities were poorly defined and the team lacked momentum. Testing could not proceed as planned because there were no test-ready deliverables available.

At the same time, numerous business units with widely differing testing requirements were waiting to conduct their acceptance tests. For an infrastructure in which every outage has an immediate impact, the requirements for transparency, coordination and traceability of the test status were correspondingly high.

 

The Turning Point: Structure Drives Progress

The Turning Point: Structure Drives Progress
The decisive impetus came not from a new tool or a different testing approach, but from a structural reorganisation of the project. New project leadership was introduced, and the project was divided into clearly defined workstreams, each with its own responsibilities.

Test management was established as a dedicated workstream with clear ownership of quality, acceptance and sign-off. From that point onwards, test management operated on an end-to-end basis:

  • The test concept was developed and agreed.

  • All participating business units were coordinated.

  • Defect management and escalation procedures were established.

  • The test status was reported regularly and in a structured manner.

his relieved the pressure on the business units. Instead of organising the testing themselves, they could focus on conducting the tests and assessing the results from a business perspective.

The result was a structured, timely testing process and a robust basis for the go-live decision.

 

Lessons Learned: Structure Leads, and So Does the Test Manager

Three important lessons emerged from this project.

  1. Firstly, projects rarely fail because of the technology.
    The decisive change in this project was organisational. Clear responsibilities, structured project management, and clearly defined roles within workstreams created the conditions required for effective test management.
  2. Secondly, a test manager is more than just a coordinator.
    In complex projects involving numerous stakeholders and tight deadlines, teams need direction, not more unanswered questions. The role requires the test manager to proactively establish structure, prepare decisions and rebuild lost trust through clear and reliable communication.
  3. Thirdly, business units want to focus on testing, not organising it.
    Taking responsibility for test organisation and establishing clear processes enables business units to focus fully on the substantive aspects of testing. This is not a 'soft' factor; it is the foundation for completing acceptance testing on schedule.

 